When there's no water, when there's dust, when there's noise. Written down in advance, for every month.
01
A whole flat, month by month
| Month | What happens | Water | Dust | Noise | Sleep there |
|---|---|---|---|---|---|
| 1 | Strip-out. The old comes out, and the terrazzo is covered. | Off from the second week | A lot | A lot, 08:00–13:00 | No |
| 2 | Pipes and wiring inside the walls. | A temporary tap in the kitchen | Some | Chasing walls, Sunday to Tuesday | No |
| 3 | Plaster, waterproofing and tiling. | Back at the end of the month | Some | A little | No |
| 4 | Joinery, the kitchen, and polishing the terrazzo. | On | A week of fine dust while polishing; the flat is closed | A little | For part of the month |
| 5 | Handover. And after a month, we come back to check. | On | None | None | Yes |
02
Three more things
A bathroom alone
Three to four weeks. You can stay at home: no shower for three weeks, and a temporary toilet from day two.
The neighbours
A letter to the neighbours and the residents' committee a week ahead. The stairwell and the lift covered. Rubble goes down every day, never piled in the yard.
The plan on the door
Every Sunday a new plan goes up inside the front door: what happens this week, who is coming, and when the water is off.

Book a survey
Book a flat survey
A two-hour survey, a written report within a week. Or just call.